BP, Milan to Wood River Pipeline Reactivation - Missouri &
Illinois
Provided the project management, design, preparation of all construction
documents, and construction coordination to convert and reactivate
a 95 mile pipeline system from crude oil to refined products. The project
included pipeline cleaning, hydrotesting, installation of a new 1,000 hp
pump station, modifications to 4 terminals, and the upgrade of 4 custody
meter facilities.
Provided project management, detailed design, and preparation of material
lists and construction documents for the rebuilding of a refined products
terminal including: new manifold, replacement of tank lines, new 150,000
barrel floating roof tank with geodesic dome, retrofit of six existing external
floating roof tanks with geodesic domes, and the addition of internal floating
roofs to existing cone roof tanks.
Enbridge Energy Terminal Re-Design Illinois
Re-design of an existing crude oil terminal to accommodate a new incoming
42 pipeline. The facilities included a 42 multiple pig launcher, relief systems,
control valve, a new 42 central manifold, addition of 42 tank lines
to existing tanks, and crude quality monitoring systems.
Designed and provided construction management to interconnect two 36
crude lines between two terminals. The work included hydraulic analysis
of the new pipelines and terminal, connection of the pipelines to two
manifolds, modifications to the existing central manifolds, addition of two
new headers, interconnection to a third party pipeline, and the addition of
a vertical can booster pump. Total footage was 1.5 miles.
Enbridge Energy, Line 64 Station Interconnect - Indiana
Provided all engineering design for the interconnection of a transmission
line to a terminal. The facilities included 1,800 feet of 24 pipeline, a receiver,
gravitometer, ultrasonic line balance meter, control valve, relief system,
interconnections to the tank manifold, and modifications to the manifold.
Enbridge Energy Pump Station Illinois
Provided project management, detailed design, preparation of material lists,
and construction documentation for a terminal origin 18,000 hp pump station,
multiple pig launcher, and ultrasonic mainline metering.
AuxSable, Propane Terminal Connection - Illinois
Designed the interconnection between a pipeline terminal and connecting
carrier. The project included two miles of new 6 pipeline, conversion of 35
miles of pipeline from natural gas to propane, design of a 4 custody meter
facility on each end of the pipeline, the interconnection of the two pipelines,
and the connections to the manifolds and propane caverns.
Project management and engineering design including preparation of
material lists and construction documents for the three new custody
transfer metering facilities.
Design-build project for the modification of two pipeline connections at
each of two propane terminal manifolds. Included was the installation
of two pig launchers, one pig receiver, and modifications to the station
piping.
Wolverine, Pipeline Terminal Metering System - Indiana
Project management, detailed design, preparation of material lists and
construction documentation for a 10 custody transfer products meter
facility and modifications to the terminal manifold system.
BP Pipelines, Line Lowering - Iowa & Indiana
Two projects to design, including all project management, to lower
multiple pipeline locations. Lowering was required to prevent thirdparty
damage in existing agriculture areas.
BP Pipelines, Relocations - Various Locations in the
Midwest United States
Provided project management, detailed design, preparation of material
lists, and construction documentation for the relocation of pipelines
ranging from 6 to 20 throughout the companys pipeline system for
public improvements.
West Shore Pipeline, Relocations - Illinois
Engineering design for the relocation of one mile each of a 12 and 16
pipeline paralleling railroad rights-of-way.
West Shore Pipeline, Relocation - Illinois
Engineering design for the relocation of a half mile of 16 pipeline for
public roadway improvements.
BP Pipelines, Crude Oil Pipeline Purge - Midwest
United States
Project management, detailed design, and preparation of construction
documentation for the purging of 330 miles of 22 crude oil pipeline
from Missouri to Indiana.
Buckeye Pipeline, As-builting - Ohio
As-built various pipeline stations and terminals. Scope of the services
performed consisted of field survey of the stations, physical measurements
of all piping and equipment, updating and redrawing the station
drawings to meet the current company drafting standards.